Home
About Us
Archives
Careers
Consulting Services
Contact Us
FREE Newsletter
 

Certificate Courses

THE Healthcare Electrician
2007 Edition

Emergency Power Supply Systems
2005-2007 Edition

 

FREE Newsletter

Click here to receive our FREE Newsletter.
 

Questions?

Have a question for one of our Advisors?
Click Here!

 

 

 

In-Phase Monitors

Q. Dan,

Your publication Healthcare Emergency Power Supply Systems (which we have purchased), was highly recommended by an advisor to JACHO. We are using your Monthly Testing Log form. As a result of a major construction-renovation project, we have a new Emergency Power System which consists of two Generac 375 KW 480/277 volt generators in parallel, synchronized to a main buss and distributed to the three branches through Asco transfer switches.

On page 177, 4.10.11 you recommend using the start button on the transfer switch to start the generators and then record the time from cold start to transfer. On page 176, 4.10.10.9, you recommend not opening the normal feed breaker to the transfer switch to simulate a power outage as that is causing one, which makes sense. However, when we use the transfer switch to initiate the test we have a transfer time of over 10 seconds because the generators see the normal power available and synchronize with it before transferring to generator power. If normal power is not available as in a normal power outage, the synchronizing will not have to take effect. The synchronizing takes approximately 7 seconds. The Generac technician feels that this amount of time is necessary to prevent events that could be electrically detrimental to the equipment served and also to the transfer equipment itself.

The Normal circuit breakers feeding the transfer switches for the Critical and Life Safety are 400 amp and 125 respectively. The only solution that I can see is to alternately (monthly) open the Normal respective circuit breaker to create an outage to reach the maximum 10 second limit; providing the circuit breakers can be documented as capable of being used on a regular basis for this purpose.

We are wondering if you have encountered this situation previously and could advise us on this matter. Thank you, D.F.

A. Age old problem….having in-phase monitors in the ATS, and then having to explain to a surveyor how they work!

As you stated the only way you can “prove” your EPSS can supply voltage to the load side of an Emergency (LS an CB) ATS is by opening a normal feed breaker to an ATS, or by disabling the in-phase monitor prior to the test.

Note that neither NFPA 99 nor 110 state that you have to “prove” the “10 second or less” time frame on any frequent basis. Therefore, I would not be inclined to use the normal feed breaker as a “test button” unless an AHJ demanded it, and took responsibility for a failure, or you thought there was a problem somewhere in the EPSS.

Reply: Thank you for your quick response. I guess that I assumed that since the “cold start to power” item was on the Testing Log form that we was required to prove the 10 second test each month. We are going to take your advice and use the test button on the transfer switch for our monthly tests and record the time even though the time is above the 10 seconds. Once a year we will open each normal feed breaker to the Critical and Life Safety and verify the 10 second test. However, if we notice an abnormality in the monthly test time, we will then proceed to open the power to the transfer switches to further investigate.

Response: Cool.

Sponsors

Blue Pillar
Bodine
Caterpillar
Leviton
Liebert
MK Plastics
Siemens
WESCO

 

Published By:

Diesel Exhaust Systems

 
 

Copyright © 2004-2005 Healthcare Engineering Network
Terms and Conditions

Questions, Comments or Support